RECOMMENDATION(S):
ADOPT Resolution No. 2020/315 accepting as complete the contracted work performed by Midstate Barrier, Inc., for the Countywide Guardrail Upgrades Project, as recommended by the Public Works Director, Brentwood, Clayton and Richmond areas. County Project No. 0662-6R4055, Federal Project No. HSIPL-5928(145) (District I, II, IV)
FISCAL IMPACT:
The Project was funded by 49% Highway Safety Improvement Program, 13% Local Road Funds (SB-1 Gas Tax), and 38% East County Area of Benefit (AOB) Funds.
BACKGROUND:
The Public Works Director reports that said work has been inspected and complies with the approved plans, special provisions and standard specifications and recommends its acceptance as complete as of September 11, 2020.
CONSEQUENCE OF NEGATIVE ACTION:
The contractor will not be paid and acceptance notification will not be recorded.
|