C. 5
To: Board of Supervisors
From: Brian M. Balbas, Public Works Director/Chief Engineer
Date: December  18, 2018
The Seal of Contra Costa County, CA
Contra
Costa
County
Subject: Notice of Completion of Construction Contract for the Phase II - Pomona Street Pedestrian Safety Improvements Project, Crockett area.

APPROVE OTHER
RECOMMENDATION OF CNTY ADMINISTRATOR RECOMMENDATION OF BOARD COMMITTEE

Action of Board On:   12/18/2018
APPROVED AS RECOMMENDED OTHER
Clerks Notes:

VOTE OF SUPERVISORS

AYE:
John Gioia, District I Supervisor
Candace Andersen, District II Supervisor
Diane Burgis, District III Supervisor
Karen Mitchoff, District IV Supervisor
Federal D. Glover, District V Supervisor
Contact: Kevin Emigh, 925-313-2233
I hereby certify that this is a true and correct copy of an action taken and entered on the minutes of the Board of Supervisors on the date shown.
ATTESTED:     December  18, 2018
David Twa,
 
BY: , Deputy

 

RECOMMENDATION(S):

ADOPT Resolution No. 2018/613 accepting as complete the contracted work performed by Sposeto Engineering, Inc., for the Phase II - Pomona Street Pedestrian Safety Improvements Project, as recommended by the Public Works Director, Crockett area. County Project No. 0662-6R4090 (District V)  

FISCAL IMPACT:

Project was funded by 43% Transportation Development Act Grant Funds and 57% Local Road Funds.  

BACKGROUND:

The Public Works Director reports that said work has been inspected and complies with the approved plans, special provisions and standard specifications and recommends its acceptance as complete as of September 17, 2018.  

BACKGROUND: (CONT'D)
  
Following the September 17, 2018 completion, PG&E was required to provide power to the flashing beacon system, which, due to no fault of the contractor, took several weeks to coordinate, schedule, and occur.  

CONSEQUENCE OF NEGATIVE ACTION:

The contractor will not be paid and acceptance notification will not be recorded.  