From: Brian M. Balbas, Public Works Director/Chief Engineer
Date: December  18, 2018
The Seal of Contra Costa County, CA
Contra
Costa
County
Subject: Notice of Completion of Construction Contract for the Bay Point Sign Upgrade Project, Bay Point area.

APPROVE OTHER
RECOMMENDATION OF CNTY ADMINISTRATOR RECOMMENDATION OF BOARD COMMITTEE

Action of Board On:   12/18/2018
APPROVED AS RECOMMENDED OTHER
Clerks Notes:

VOTE OF SUPERVISORS

AYE:
John Gioia, District I Supervisor
Candace Andersen, District II Supervisor
Diane Burgis, District III Supervisor
Karen Mitchoff, District IV Supervisor
Federal D. Glover, District V Supervisor
Contact: Kevin Emigh, 925-313-2233
I hereby certify that this is a true and correct copy of an action taken and entered on the minutes of the Board of Supervisors on the date shown.
ATTESTED:     December  18, 2018
David Twa,
 
BY: , Deputy

 

RECOMMENDATION(S):

ADOPT Resolution No. 2018/610 accepting as complete the contracted work performed by Statewide Traffic Safety and Signs, Inc., for the Bay Point Sign Upgrade Project, as recommended by the Public Works Director, Bay Point area. County Project No. 0662-6R4024-18 (District V)  
  

FISCAL IMPACT:

Project was funded by 90.5% Highway Safety Improvement Program Grant Funds and 9.5% Local Road Funds.  
  



BACKGROUND:

The Public Works Director reports that said work has been inspected and complies with the approved plans, special provisions and standard specifications and recommends its acceptance as complete as of October 22, 2018.  
  

CONSEQUENCE OF NEGATIVE ACTION:

The contractor will not be paid and acceptance notification will not be recorded.  
  