RECOMMENDATION(S):
APPROVE and AUTHORIZE the Interim Public Works Director, or designee, to execute Contract Change Order No. 1 (CCO #1) with Engineered Soil Repairs, Inc., to increase the payment limit from $300,000 to $600,000, and to extend the completion date from December 6, 2017 to December 8, 2018, for the 2017 On-Call Contract for Various Road, Flood Control, and Airport Maintenance Work, Countywide.
FISCAL IMPACT:
100% Local Road, Flood Control District and Airport Funds.
BACKGROUND:
On December 6, 2016, the County awarded an on-call contract to Engineered Soil Repairs, Inc., in a not-to-exceed amount of $300,000, and unit prices submitted in the bid ($1,614.25 Total Unit Price), for various road, flood control, and airport maintenance work to supplement the maintenance crews’ routine and emergency work.
|