RECOMMENDATION(S):
APPROVE and AUTHORIZE the Conservation and Development Director, or designee, to execute a contract amendment with Cardno, Inc., to extend the term of Contract #47772 from December 31, 2016 through December 31, 2018, with no change in the payment limit of $434,521, to provide continued service for the completion of the environmental impact report (EIR) for the Shell Martinez Refinery's Greenhouse Gas Reduction Project (County File #LP14-2006).
FISCAL IMPACT:
There is no impact to the General Fund. All application, environmental review, and project processing costs and fees are to be paid by the project applicant.
|