PDF Return
C. 5
To: Board of Supervisors
From: Julia R. Bueren, Public Works Director/Chief Engineer
Date: December  8, 2015
The Seal of Contra Costa County, CA
Contra
Costa
County
Subject: Approve the third extension for Road Improvement Agreement RA06-01208, San Ramon (Dougherty Valley) area.

APPROVE OTHER
RECOMMENDATION OF CNTY ADMINISTRATOR RECOMMENDATION OF BOARD COMMITTEE

Action of Board On:   12/08/2015
APPROVED AS RECOMMENDED OTHER
Clerks Notes:

VOTE OF SUPERVISORS

AYE:
John Gioia, District I Supervisor
Candace Andersen, District II Supervisor
Mary N. Piepho, District III Supervisor
Karen Mitchoff, District IV Supervisor
Federal D. Glover, District V Supervisor
Contact: Jocelyn A.B. LaRocque, 925-313-2315
cc: J. A.B. LaRocque - Engineering Services     D. Roberts, Engineering Services Originator     Design/Construction Division     Current Planning - DCD     Shapell Homes, , 6800 Koll Center Pkwy., Ste. 320, Pleasanton, CA 94566     National Fire Insur. Co. of Hartford 100 Matsonford Rd, #200 Radnor PA 19087     T - 9-18-16    
I hereby certify that this is a true and correct copy of an action taken and entered on the minutes of the Board of Supervisors on the date shown.
ATTESTED:     December  8, 2015
David Twa,
 
BY: , Deputy

 

RECOMMENDATION(S):

ADOPT Resolution No. 2015/436 approving the third extension of the Road Improvement Agreement for road acceptance RA06-01208 (cross-reference SD04-08856), for a project being developed by Shapell Homes, a Division of Shapell Industries, Inc., a Delaware Corporation, as recommended by the Public Works Director, San Ramon (Dougherty Valley) area. (District II)  

FISCAL IMPACT:

No fiscal impact.

BACKGROUND:

The terminal date of the Road Improvement Agreement needs to be extended. The developer has not completed the required improvements and has requested more time. (Approximately 80% of the work has been completed to date.) By granting an extension, the County will give the developer more time to complete his improvements and keep the bond current.


CONSEQUENCE OF NEGATIVE ACTION:

The term date of the Road Improvement Agreement will not be extended and the developer will be in default of the agreement, requiring the County to take legal action against the developer and surety to get the improvements installed.

CHILDREN'S IMPACT STATEMENT:

AgendaQuick©2005 - 2024 Destiny Software Inc., All Rights Reserved