PDF Return
C. 4
To: Board of Supervisors
From: Julia R. Bueren, Public Works Director/Chief Engineer
Date: December  15, 2009
The Seal of Contra Costa County, CA
Contra
Costa
County
Subject: Accepting completion of improvements, MS 90-00141, San Ramon area.

APPROVE OTHER
RECOMMENDATION OF CNTY ADMINISTRATOR RECOMMENDATION OF BOARD COMMITTEE

Action of Board On:   12/15/2009
APPROVED AS RECOMMENDED OTHER
Clerks Notes:Seven Speakers, Matt Trost, Michael Warholic, James A. Warholic, Patrick WarholicCharles Farr, Michael L. Rains, and Lori Farr,

VOTE OF SUPERVISORS

AYE:
John Gioia, District I Supervisor
Gayle B. Uilkema, District II Supervisor
Mary N. Piepho, District III Supervisor
Susan A. Bonilla, District IV Supervisor
Federal D. Glover, District V Supervisor
Contact: J. LaRocque - 3-2315
cc: D. Favero, Engineering Services,     A. Bell, Construction,     E. Sanders, M & T Lab,     P. Edwards, Engineering Services,    
I hereby certify that this is a true and correct copy of an action taken and entered on the minutes of the Board of Supervisors on the date shown.
ATTESTED:     December  15, 2009
David Twa,
 
BY: , Deputy

 

RECOMMENDATION(S):

ADOPT Resolution No. 2009/572 accepting completion of private improvements, for MS 90-00141, for project being developed by Charles M. Farr and Lorraine A. Farr, as recommended by the Public Works Director, San Ramon area.

FISCAL IMPACT:

No fiscal impact.

BACKGROUND:

The developer completed the private improvements required of the minor subdivision.

CONSEQUENCE OF NEGATIVE ACTION:

The private improvements will not be accepted as complete, the developer will not receive a refund of their cash deposit, the Subdivision Agreement and performance/maintenance surety (letter of credit) will not be exonerated.







AgendaQuick©2005 - 2024 Destiny Software Inc., All Rights Reserved