C. 90
To: Board of Supervisors
From: Brian M. Balbas, Public Works Director/Chief Engineer
Date: November  29, 2022
The Seal of Contra Costa County, CA
Contra
Costa
County
Subject: Consulting Services Agreement with Vanir Construction Management, Inc., Countywide.

APPROVE OTHER
RECOMMENDATION OF CNTY ADMINISTRATOR RECOMMENDATION OF BOARD COMMITTEE

Action of Board On:   11/29/2022
APPROVED AS RECOMMENDED OTHER
Clerks Notes:

VOTE OF SUPERVISORS

AYE:
John Gioia, District I Supervisor
Candace Andersen, District II Supervisor
Diane Burgis, District III Supervisor
Karen Mitchoff, District IV Supervisor
Federal D. Glover, District V Supervisor
Contact: Carl Roner - (925) 313-2213
cc: Jocelyn LaRocque- Engineering Services     Carl Roner- Special Districts     Rochelle Johnson - Special Districts     Scott Anderson - Special Districts     Jeff Acuff-Capital Projects    
I hereby certify that this is a true and correct copy of an action taken and entered on the minutes of the Board of Supervisors on the date shown.
ATTESTED:     November  29, 2022
Monica Nino, County Administrator
 
BY: , Deputy

 

RECOMMENDATION(S):

APPROVE and AUTHORIZE the Public Works Director, or designee, to execute a Consulting Services Agreement (contract) with Vanir Construction Management, Inc., in an amount not to exceed $1,000,000, to provide on-call project management services for the period December 1, 2022, through November 30, 2025, Countywide.

FISCAL IMPACT:

Work performed under this contract is 100% funded by Federal, Local, State and/or General Funds. (100% Various Funds)

BACKGROUND:

The Public Works Department is involved in various projects in the County, which require project management services for capital improvement projects. After a solicitation process, this firm was selected as one of five firms to provide project management services on an “on-call” basis. The consultant will augment Public Works staff during busy times when extra help is needed or when in-house expertise is not available. This on-call contract will be in effect for three years. Government code section 31000 authorizes the County to enter into contract for consultant services.



CONSEQUENCE OF NEGATIVE ACTION:

If the contract is not approved, necessary capital projects may not be completed in a timely manner, which may jeopardize funding and delay design and construction of various capital projects.