RECOMMENDATION(S):
APPROVE and AUTHORIZE the Public Works Director, or designee, to execute on behalf of the County, a Utility Agreement with Contra Costa Water District (District), effective November 9, 2021, to require the District to pay approximately $550,000 in connection with utility relocation for the Marsh Creek Road Bridges (#28C0143 & 28C0145) Replacement Project (Project), Clayton and Brentwood areas. County Project No. 0662-6R4083 / Federal Project No. BRLS 5928(125) (District III and IV)
FISCAL IMPACT:
The estimated cost for the work associated with this agreement is $550,000.00. The District will be responsible for the entire cost. (100% Contra Costa Water District funds)
|