To: Board of Supervisors
From: Brian M. Balbas, Public Works Director/Chief Engineer
Date: November  17, 2020
The Seal of Contra Costa County, CA
Contra
Costa
County
Subject: Execute a contract with MNS Engineers Inc., to provide on-call land development engineering services, Countywide.

APPROVE OTHER
RECOMMENDATION OF CNTY ADMINISTRATOR RECOMMENDATION OF BOARD COMMITTEE

Action of Board On:   11/17/2020
APPROVED AS RECOMMENDED OTHER
Clerks Notes:

VOTE OF SUPERVISORS

AYE:
John Gioia, District I Supervisor
Candace Andersen, District II Supervisor
Diane Burgis, District III Supervisor
Karen Mitchoff, District IV Supervisor
Federal D. Glover, District V Supervisor
Contact: Randolf Sanders (925) 313-2111
cc: Warren Lai - Deputy     Slava Gospodchikov - Engineering Services     Larry Gossett- Engineering Services     Randolf Sanders- Engineering Services     Samantha Fithan- Administration     Michael Mann- Finance     MNS Engineers, Inc. - Consultant    
I hereby certify that this is a true and correct copy of an action taken and entered on the minutes of the Board of Supervisors on the date shown.
ATTESTED:     November  17, 2020
David Twa,
 
BY: , Deputy

 

RECOMMENDATION(S):

APPROVE and AUTHORIZE the Public Works Director, or designee, to execute a contract with MNS Engineers, Inc., in an amount not to exceed $250,000 to provide on-call land development engineering services for the period December 1, 2020 to November 30, 2023, Countywide. (All Districts) Project No.: Various.  

FISCAL IMPACT:

100% Developer Fees.

BACKGROUND:

The Public Works Department is involved in the review of land development projects throughout the County. As part of this regular work, consultant services are required to augment staff and provide special technical assistance on an on-call basis. After a solicitation process, MNS Engineers, Inc. was one of two firms selected to provide land development engineering services. These services include researching, writing, reviewing, and preparing conditions of approval for land development entitlements, as well as plan checking for conditions of approval compliance.



CONSEQUENCE OF NEGATIVE ACTION:

Without the approval of the Board of Supervisors, the Public Works Department will be unable to complete land development engineering projects in a timely manner, therefore delaying completion of current and future land development projects.  
  