RECOMMENDATION(S):
APPROVE the Buchanan Airport Taxiway Echo & Kilo Improvements Project contingency fund increase of $90,000 for a new contingency fund total of $245,996.10, and a new payment limit of $1,805,957.10, effective November 7, 2017, as recommended by the Interim Public Works Director, Concord area. Project No. 4855-4653-SAS-6X5322, Federal Project No. AIP 3-06-0050-021.
FISCAL IMPACT:
Extra work is being funded by 100% Airport Enterprise Funds.
BACKGROUND:
Additional funds are necessary to pay the contractor, Granite Rock Company, for additional costs to be incurred as the result of adding paving to the project’s scope at the request of our Airport Division.
|