cash submitted for security shall be returned.
(7) AUTHORIZE the Public Works Director, or designee, to sign any escrow agreements prepared for this project to permit the direct payment of retentions into escrow or the substitution of securities for moneys withheld by the County to ensure performance under the contract, pursuant to Public Contract Code Section 22300.
(8) AUTHORIZE the Public Works Director, or designee, to order changes or additions to the work pursuant to Public Contract Code Section 20142.
(9) DELEGATE, pursuant to Public Contract Code Section 4114, to the Public Works Director, or designee, the Board’s functions under Public Contract Code Sections 4107 and 4110.
(10) DECLARE that, should the award of the contract to Overaa be invalidated for any reason, the Board would not in any event have awarded the contract to any other bidder, but instead would have exercised its discretion to reject the bid received.
100% Hospital Enterprise Funds.
The main purpose of this project is to expand the Emergency Department (ED) fast track area at the Contra Costa Regional Medical Center (CCRMC) to help decrease the number of annual patient visits to the ED. Currently, the ED is operating at twice the design capacity.
The project, which involves approximately 5,960 square feet of interior modifications and improvements for fast track and patient triage on the third floor (Emergency and Imaging Departments), will result in reconfiguration of waiting and reception, triage and registration, exam rooms, medication room, radiology reading room, offices and work areas requiring new partitions, suspended ceilings, flooring, painting, casework, plumbing, HVAC, electrical, telephone/data communications, etc. The area of interior improvements is located in the west side of the five-story hospital building.
Plans and specifications for the project have been prepared for the Public Works Department by HDR Architecture, Inc. and have been filed with the Clerk of the Board by the Public Works Director. The construction cost estimate is $3,079,000, and the general prevailing wage rates are on file with the Clerk of the Board of Supervisors and will be the minimum rates paid on this project. Bids were received and opened by the Public Works Department on October 22, 2015, and the bid results are as follows:
BIDDER |
BASE BID |
C. Overaa & Co., Richmond |
$1,846,000 |
Vila Construction Co., Richmond |
$1,898,158 |
Taber Construction, Concord |
$1,910,000 |
All three bids were below the Architect's Estimate of $3,079,000. Staff has evaluated the low bid submitted by Overaa and their good faith effort documentation. Staff has determined that Overaa's bid is responsive and their good faith effort documentation is in compliance with the County's Outreach Program. The Public Works Director recommends that the Board award the construction contract for this project to Overaa, the lowest responsible and responsive bidder, in the amount of $1,846,000, which is $1,233,000 less than the Architect’s Estimate.
The general prevailing rates of wages, which shall be the minimum rates paid on this project, are on file with the Clerk of the Board, and copies are available to any party upon request.
If this project is not approved and authorized, the Emergency Department at the Contra Costa Regional Medical Center will continue to operate at twice the design capacity.