RECOMMENDATION(S):
APPROVE Appropriation Adjustment No.5012, transferring $4,005,000 to Public Works-Airport (0843), Department of Information Technology (0147), Human Resources (0035), Treasurer-Tax Collector (0015) for fiscal year 2022-23 Venture Capital Projects.
FISCAL IMPACT:
Project funds are budgeted in the General Fund Contingency for FY 2022-23 (100% General Fund).
BACKGROUND:
The Board of Supervisors adopted a Budget Policy in 2006, which included a resource intended to improve departmental operations. Per this policy, in FY 2022-23 funding was made available for technology projects to be used to increase efficiencies and economies in departments that did not have resources available within their normal operating budgets for such expense. Requests for these funds were submitted with the Departments' baseline budgets. Departments included requests of $6,896,923 and the County Administrator was able to approve $4,005,000.
|