C. 7
To: Board of Supervisors
From: Greg Baer, Director of Airports
Date: October  4, 2022
The Seal of Contra Costa County, CA
Contra
Costa
County
Subject: Increase Payment Limit for Construction Contract with W.E. Lyons Construction Company

APPROVE OTHER
RECOMMENDATION OF CNTY ADMINISTRATOR RECOMMENDATION OF BOARD COMMITTEE

Action of Board On:   10/04/2022
APPROVED AS RECOMMENDED OTHER
Clerks Notes:

VOTE OF SUPERVISORS

AYE:
John Gioia, District I Supervisor
Candace Andersen, District II Supervisor
Diane Burgis, District III Supervisor
Karen Mitchoff, District IV Supervisor
Federal D. Glover, District V Supervisor
Contact: Russell Milburn, (925) 681-4200
I hereby certify that this is a true and correct copy of an action taken and entered on the minutes of the Board of Supervisors on the date shown.
ATTESTED:     October  4, 2022
Monica Nino, County Administrator
 
BY: , Deputy

 

RECOMMENDATION(S):

APPROVE and AUTHORIZE the Director of Airports, or designee, to execute an amendment to the May 12, 2021, contract with W.E. Lyons Construction Company (W.E. Lyons), to increase the payment limit by an amount not to exceed $700,000, to a new payment limit of $14,633,040, in order to address two critical utility components.  

FISCAL IMPACT:

There is no impact to the General Fund; the increased cost is fully funded by a combination of Federal Aviation Administration (FAA) grants and Airport Enterprise Funds (approximately 66% FAA, 34% Airport Enterprise Fund).

BACKGROUND:

Two critical utility components for the Aircraft Rescue and Firefighting facility, terminal, and administrative office (Terminal) at Buchanan Field Airport need to be updated: (1) $375,000 to connect to PG&E power from the requisite three-phase power supply to the building; and (2) $325,000 to install a sewer lift station to ensure proper sewage flow. The need for a lift station was determined after the project was bid and under construction. The combined $700,000 for utility improvements are required in order to complete construction of the Terminal.


CONSEQUENCE OF NEGATIVE ACTION:

If the Board does not approve the construction contract amendment to include the two critical utility improvements, the Terminal cannot be completed.