RECOMMENDATION(S):
APPROVE and AUTHORIZE the Public Works Director, or designee, to execute Contract Change Order No. 2 with American Pavement Systems, Inc., in an amount not to exceed $325,000, Alamo, El Sobrante, and North Richmond areas. Project No. 0672-6U2185 (District I, II, IV)
FISCAL IMPACT:
The Project is being funded by 100% Local Road Funds.
BACKGROUND:
Contract Change Order No. 2, is necessary to pay the contractor, American Pavement Systems, Inc., for additional costs incurred as a result of adding additional streets, and a calculating error discovered determining total square yardage of roads to be slurry sealed. The change order is necessary to compensate the contractor for additional traffic control, construction area signs and clearing and grubbing.
CONSEQUENCE OF NEGATIVE ACTION:
The lack of approval would prevent successful completion of this contract.
|