RECOMMENDATION(S):
APPROVE and AUTHORIZE the Public Works Director, or designee, to execute a contract amendment with Vanir Construction Management, Inc. (Vanir), effective October 20, 2020, to increase the payment limit by $845,052 to a new payment limit of $11,250,000, with no change to the termination date of May 9, 2023, for construction management services for the renovation of Module M at the Martinez Detention Facility, 1000 Ward Street, Martinez area.
FISCAL IMPACT:
The contract amount amendment, not to exceed $845,052, is part of the approved general purpose revenue/reserves budget (100% General Fund).
BACKGROUND:
The County awarded a contract to Vanir Construction Management, Inc., for construction management services for two sites at a total allotted amount of $6,000,000, with a completion date of 3 years from the effective date of May 9, 2017.
|