RECOMMENDATION(S):
ADOPT Resolution No. 2016/580 accepting as complete the contracted work performed by Pavement Coatings Co., for the 2016 Slurry Seal Project, as recommended by the Public Works Director, Alamo, Clayton, Diablo and Walnut Creek areas. Project No. 0672-6U2153-16 (Districts II, III, IV)
FISCAL IMPACT:
Project was funded by 100% Local Road Funds.
BACKGROUND:
The Public Works Director reports that said work has been inspected and complies with the approved plans, special provisions and standard specifications and recommends its acceptance as complete as of September 29, 2016.
|