PDF Return
C. 1
To: Board of Supervisors
From: Julia R. Bueren, Public Works Director/Chief Engineer
Date: October  20, 2015
The Seal of Contra Costa County, CA
Contra
Costa
County
Subject: APPROVE Contract Amendment No. 1 with DKS Associates.

APPROVE OTHER
RECOMMENDATION OF CNTY ADMINISTRATOR RECOMMENDATION OF BOARD COMMITTEE

Action of Board On:   10/20/2015
APPROVED AS RECOMMENDED OTHER
Clerks Notes:

VOTE OF SUPERVISORS

AYE:
John Gioia, District I Supervisor
Candace Andersen, District II Supervisor
Mary N. Piepho, District III Supervisor
Karen Mitchoff, District IV Supervisor
Federal D. Glover, District V Supervisor
Contact: Mary Halle (925)313-2327
I hereby certify that this is a true and correct copy of an action taken and entered on the minutes of the Board of Supervisors on the date shown.
ATTESTED:     October  20, 2015
David Twa,
 
BY: , Deputy

 

RECOMMENDATION(S):

APPROVE and AUTHORIZE the Public Works Director, or designee, to execute a contract amendment with DKS Associates to extend the termination date from October 23, 2015, to April 23, 2017, and increase the payment limit by $170,000 to a new payment limit of $820,000, to provide Area of Benefit (AOB) Program Updates, Countywide. (100% Area of Benefit Funds)

FISCAL IMPACT:

100% Area of Benefit Funds.

BACKGROUND:

On October 23, 2012, the Board of Supervisors approved a contract with DKS Associates to provide Transportation AOB Update Consultant services. Transportation Engineering staff recommends extending the contract term from October 23, 2015 to April 23, 2017, with an increase to the original payment limit of $170,000, for a total of $820,000 to allow for completion of the Consultant’s work on the AOB Program Updates

CONSEQUENCE OF NEGATIVE ACTION:

Without Board approval, the County will not be able to complete the work on the AOB Program Updates.


CHILDREN'S IMPACT STATEMENT:

Not Applicable.