RECOMMENDATION(S):
APPROVE and AUTHORIZE the Public Works Director, or designee, to execute a contract amendment with DKS Associates to extend the termination date from October 23, 2015, to April 23, 2017, and increase the payment limit by $170,000 to a new payment limit of $820,000, to provide Area of Benefit (AOB) Program Updates, Countywide. (100% Area of Benefit Funds)
FISCAL IMPACT:
100% Area of Benefit Funds.
BACKGROUND:
On October 23, 2012, the Board of Supervisors approved a contract with DKS Associates to provide Transportation AOB Update Consultant services. Transportation Engineering staff recommends extending the contract term from October 23, 2015 to April 23, 2017, with an increase to the original payment limit of $170,000, for a total of $820,000 to allow for completion of the Consultant’s work on the AOB Program Updates
CONSEQUENCE OF NEGATIVE ACTION:
Without Board approval, the County will not be able to complete the work on the AOB Program Updates.
|