RECOMMENDATION(S):
APPROVE and AUTHORIZE the Public Works Director, or designee, to execute Contract Change Order No. 1 with Drake Construction, LLC, effective January 10, 2023, to increase the payment limit by $39,678.00, to a new payment limit of $464,678.00, for the Deputy Workstation Replacement Project at the Martinez Detention Facility and West County Detention Facility (WO#6643568 and WO#6643572), Martinez and Richmond areas.
FISCAL IMPACT:
The total estimated construction cost will be funded by the Board of State and Community Corrections Coronavirus Emergency Supplemental Funding Grant (BSCC CESF).
BACKGROUND:
Contract Change Order No. 1, is necessary to pay the contractor, Drake Construction, LLC., for the material price increase for two materials that escalated 7.13% between the time period of December 2021 (Bid Opening) to August 2022 (Contract Execution).
|