RECOMMENDATION(S):
ADOPT Resolution No. 2020/18 accepting as complete the contracted work performed by Ghilotti Bros., Inc., for the Camino Tassajara Bike Lane Gap Closure Project, as recommended by the Public Works Director, San Ramon area. County Project No. 0662-6R4010 (District III)
FISCAL IMPACT:
The Project was funded by Tri-Valley Transportation Council Funds 32.5%; Measure J Funds 25%; South County Area of Benefit Funds 25%, and Southern Contra Costa Subregional Fee Program 17.5%.
BACKGROUND:
The Public Works Director reports that said work has been inspected and complies with the approved plans, special provisions and standard specifications and recommends its acceptance as complete as of November 12, 2019.
CONSEQUENCE OF NEGATIVE ACTION:
The contractor will not be paid and acceptance notification will not be recorded.
|