PDF Return
C. 4
To: Board of Supervisors
From: Brian M. Balbas, Public Works Director/Chief Engineer
Date: January  15, 2019
The Seal of Contra Costa County, CA
Contra
Costa
County
Subject: Notice of Completion of Construction Contract for the Pedestrian Crossing Enhancements – Central and East County Project

APPROVE OTHER
RECOMMENDATION OF CNTY ADMINISTRATOR RECOMMENDATION OF BOARD COMMITTEE

Action of Board On:   01/15/2019
APPROVED AS RECOMMENDED OTHER
Clerks Notes:

VOTE OF SUPERVISORS

AYE:
John Gioia, District I Supervisor
Candace Andersen, District II Supervisor
Diane Burgis, District III Supervisor
Karen Mitchoff, District IV Supervisor
Federal D. Glover, District V Supervisor
Contact: Kevin Emigh, 925-313-2233
I hereby certify that this is a true and correct copy of an action taken and entered on the minutes of the Board of Supervisors on the date shown.
ATTESTED:     January  15, 2019
David Twa,
 
BY: , Deputy

 

RECOMMENDATION(S):

ADOPT Resolution No. 2019/6 accepting as complete the contracted work performed by Tennyson Electric, Inc., for the Pedestrian Crossing Enhancements – Central and East County Project, as recommended by the Public Works Director, Bay Point, Discovery Bay, Knightsen and Walnut Creek areas. County Project No. 0662-6R4112 (District III, IV, and V)  

FISCAL IMPACT:

Project was funded by 36% Transportation Development Act Grant Funds and 64% Local Road Funds.  

BACKGROUND:

The Public Works Director reports that said work has been inspected and complies with the approved plans, special provisions and standard specifications and recommends its acceptance as complete as of October 5, 2018.  



CONSEQUENCE OF NEGATIVE ACTION:

The contractor will not be paid and acceptance notification will not be recorded.  

AgendaQuick©2005 - 2024 Destiny Software Inc., All Rights Reserved