RECOMMENDATION(S):
APPROVE the Balfour Road Shoulder Widening contingency fund increase of $290,000 for a new contingency fund total of $715,432.20, and a new payment limit of $4,969,754.20, effective January 9, 2018, as recommended by the Interim Public Works Director; and
AUTHORIZE the Interim Public Works Director, or designee, to execute Contract Change Order No. 4, Supplement 1, with Granite Rock Company, effective January 9, 2018, in an amount not to exceed $380,000, Brentwood area. Project No. 0662-6R4002 (District III)
FISCAL IMPACT:
100% Discovery Bay West Mitigation Fees.
|