RECOMMENDATION(S):
APPROVE and AUTHORIZE the Public Works Director, or designee, to execute a contract amendment with Ghirardelli Associates, Inc., effective June 1, 2015, to update payment provisions with no change to original term or payment limit of $442,000 for construction management services for the San Pablo Dam Road Walkability Project, El Sobrante area.
FISCAL IMPACT:
This project is funded by 44% Transportation for Livable Communities Funds, 16% Proposition 1B Funds, and 40% Local Road Funds.
BACKGROUND:
The Public Works Director, or designee, executed a consulting services agreement (CSA), dated August 12, 2014, with Ghirardelli Associates Inc., for construction management services for the San Pablo Dam Road Walkability Project.
|