RECOMMENDATION(S):
ADOPT Resolution No. 2013/41 accepting as complete the construction contract work performed by Pace Drywall, Inc. for Trade Package 3C, consisting of drywall/plaster for the West County Health Center project, 13601 San Pablo Avenue, San Pablo, for the Health Services Department, as recommended by the Public Works Director.
DIRECT the Clerk of the Board to file with the County Recorder a certified copy of Resolution No. 2013/41 no later than ten (10) days after adoption.
FISCAL IMPACT:
There is no direct fiscal impact resulting from the adoption of the Resolution of Acceptance and Notice of Completion, but the adoption and recording will limit the period for filing stop payment notices and bond claims on this trade contract.
|