C. 2
To: Board of Supervisors
From: Julia R. Bueren, Public Works Director/Chief Engineer
Date: January  10, 2012
The Seal of Contra Costa County, CA
Contra
Costa
County
Subject: ACCEPTANCE & Giving Notice of Completion of Contract for Market Avenue Sidewalk Improvements, Project No. 0662-6R4116

APPROVE OTHER
RECOMMENDATION OF CNTY ADMINISTRATOR RECOMMENDATION OF BOARD COMMITTEE

Action of Board On:   01/10/2012
APPROVED AS RECOMMENDED OTHER
Clerks Notes:

VOTE OF SUPERVISORS

AYE:
John Gioia, District I Supervisor
Mary N. Piepho, District III Supervisor
Karen Mitchoff, District IV Supervisor
Federal D. Glover, District V Supervisor
ABSENT:
Gayle B. Uilkema, District II Supervisor
Contact: Kevin Emigh, (925) 313-2233
cc: J. Dowling, Construction     P. Denison, Finance     Malachi Paving & Grading     Kathy Guruwaya    
I hereby certify that this is a true and correct copy of an action taken and entered on the minutes of the Board of Supervisors on the date shown.
ATTESTED:     January  10, 2012
David Twa,
 
BY: , Deputy

 

RECOMMENDATION(S):

ADOPT Resolution No. 2012/4 accepting as complete the contracted work performed by Malachi Paving & Grading, Inc., for the Market Avenue Sidewalk Improvements project, Project No. 0662-6R4116, as recommended by the Public Works Director.

FISCAL IMPACT:

The project construction was funded by 38% Transportation Development Act funds, 33% Redevelopment funds, 16% Local funds, and 13% Community Development Block Grant funds.

BACKGROUND:

The Public Works Director reports that said work has been inspected and complies with the approved plans, special provisions and standard specifications and recommends its acceptance as complete as of December 2, 2011.

CONSEQUENCE OF NEGATIVE ACTION:

The contractor will not be paid and acceptance notification will not be recorded.

CHILDREN'S IMPACT STATEMENT:

Not Applicable.