PDF Return
C. 3
To: Board of Supervisors
From: Julia R. Bueren, Public Works Director/Chief Engineer
Date: January  26, 2010
The Seal of Contra Costa County, CA
Contra
Costa
County
Subject: APPROVE Pacheco Boulevard Sidewalk (Windhover Way to Goree Court) Project.

APPROVE OTHER
RECOMMENDATION OF CNTY ADMINISTRATOR RECOMMENDATION OF BOARD COMMITTEE

Action of Board On:   01/26/2010
APPROVED AS RECOMMENDED OTHER
Clerks Notes:

VOTE OF SUPERVISORS

AYE:
John Gioia, District I Supervisor
Gayle B. Uilkema, District II Supervisor
Mary N. Piepho, District III Supervisor
Susan A. Bonilla, District IV Supervisor
Federal D. Glover, District V Supervisor
Contact: Ave Brown (925) 313 - 2311
cc: Emma Kuevor, Affirmative Action Officer     Stephen Ybarra, Auditor Controller     Sylvia Alcantar, DCD     Paulette Denison, Finance     Jessie Duffy, TE     Marlon Epps, Environmental    
I hereby certify that this is a true and correct copy of an action taken and entered on the minutes of the Board of Supervisors on the date shown.
ATTESTED:     January  26, 2010
David Twa,
 
BY: , Deputy

 

RECOMMENDATION(S):

APPROVE the Pacheco Boulevard Sidewalk (Windhover Way to Goree Court) Project and AUTHORIZE the Public Works Director, or designee, to advertise the project [DCD-CP#09-94] Project No.: 0676-6P1025.   
  

FIND the project is a California Environmental Quality Act (CEQA), Class 1(c) Categorical Exemption, pursuant to Section 15301(c) of the CEQA Guidelines, and  

  




RECOMMENDATION(S): (CONT'D)
DIRECT the Director of Conservation and Development to file a Notice of Exemption with the County Clerk, and   
  
AUTHORIZE the Public Works Director to arrange for payment of a $25 fee to the Department of Conservation and Development for processing, and a $50 fee to the County Clerk for filing the Notice of Exemption.

FISCAL IMPACT:

There is no impact to the County General Fund. This project is funded by Local Road Funds (100%).

BACKGROUND:

This project is necessary to provide pedestrian and bicycle facilities along Pacheco Boulevard between Windhover Way and Goree Court. These improvements are also needed to provide access for the mobility impaired.

CONSEQUENCE OF NEGATIVE ACTION:

Delay in approving the project will result in a delay of design and construction and may jeopardize funding.