Receive update from the Aviation Advisory Committee Chair (Maurice Gunderson)
|
|
Maurice Gunderson Reported:
-
Reported aircraft noise at normal levels
-
Tower staff hours back to normal
-
Working on an aviation fuel distribution project which would require a significant coordinated sales effort by the county.
-
Supervisor Mitchoff requested to be advised of updates regarding aviation fuel distribution project.
|
|
|
|
|
|
|
|
5.
|
|
|
|
Discuss progress regarding the Byron Airport General Plan Amendment (Daniel Barrios, Department of Conservation and Development)
|
|
-
Dudek provided traffic impact analysis to Public Works transportation, DCD Transportation in November 2020.
-
Meeting held by Public Works, DCD and Dudek to discuss traffic impact analysis report and the received comments. Majority of comments were resolved or clearly communicated to Dudek.
-
Contract extended for Dudek until end of 2021.
-
February 11th final memo with proposed solutions sent to Dudek with comments.
-
Supervisors Mitchoff and Burgis requested to be advised of any changes with Dudek even if there is no Airport Committee meeting.
-
An additional $200,000 is needed from the Mariposa Community Benefits fund to cover county staff time to complete project
-
Supervisor Mitchoff requested a detailed breakdown of the contract and use of the Mariposa funds for the project.
|
|
|
|
|
|
|
|
6.
|
|
|
|
Discuss Runway 14L/32R Pavement Replacement Project, Buchanan Field Airport
|
|
-
Project completion accepted 3/9/21 by Board of Supervisors
-
35-day window for sub-contractors to submit claims.
-
Project was completed on time and under budget.
|
|
|
|
|
|
|
|
7.
|
|
|
|
Discuss the Airport Innovation and Business Attraction Program, Buchanan Field and Byron Airport
|
|
-
Urban Air Mobility Project broke ground on construction of 2 large hangars at Byron Airport
-
EssentialAero has been testing Unmanned Aircraft Systems at both Airports
|
|
|
|
|
|
|
|
8.
|
|
|
|
Discuss Airport's Project Development Update |
|
|
|
|
|
|
|
|
a. |
|
|
Discuss Proposed Development of 4.1-acre phase 1 aeronautical use at, Byron Airport
|
|
-
Urban Air Mobility project broke ground on first segment of phase 1.
-
There are two other phases in this project which includes 3 more large hangars and up to 12 smaller hangars
|
|
|
|
|
|
|
|
|
b. |
|
|
Discuss ARFF/Storage Building, Byron Airport
|
|
-
ARFF building project broke ground.
-
Utility relocation completed
|
|
|
|
|
|
|
|
|
c. |
|
|
Discuss Con Fire Station 9 to Airport property, Buchanan Field
|
|
-
Working with FAA to release the land for non-aeronautical use to allow a fire station with an aircraft hangar
-
Air ambulance component is deemed an aeronautical use by FAA
|
|
|
|
|
|
|
|
|
d. |
|
|
Discuss Development of 16-acres non-aeronautical use, Buchanan Field
|
|
-
Sub-tenant will have an update in 2-3 weeks
-
Groundbreaking desired by end of 2022/early 2023
|
|
|
|
|
|
|
|
|
e. |
|
|
Discuss 0.86-acre Development at Buchanan Field
|
|
-
Competitive solicitations ended last week
-
No additional letters of competitive interest were received
|
|
|
|
|
|
|
|
|
f. |
|
|
Terminal Building, Buchanan Field
|
|
-
Construction bids received back 3/11/21
-
Construction to begin mid-summer 2021
-
Expected project completion Fall 2022
|
|
|
|
|
|
|
|
9.
|
|
|
|
Discuss Security Project, Buchanan Field
|
|
-
Grant received from FAA in the amount of 3.2 Million
-
Bid opening April 6, 2021
-
Mid-summer start construction
-
Design completed and approved by Board of Supervisors February 9, 2021
|
|
|
|
|
|
|
|
10.
|
|
|
|
Discuss Next FAA/Caltrans grant request Buchanan Field Airport master plan
|
|
Information Item
-
Runway Safety Improvement Projects
-
Airport master plan
|
|
|
|
|
|
|
|