RECOMMENDATION(S):
ADOPT Resolution No. 2022/141 approving and authorizing the Public Works Director, or designee, to fully close a portion of Springbrook Road between Gilmore Court and Sherwood Way, on June 1, 2022 through September 1, 2022 from 7:00 a.m. through 5:00 p.m., for installation of East Bay Municipal Utility District water main and accompanying infrastructure (Infrastructure Renewal Project), Walnut Creek area. (District IV)
FISCAL IMPACT:
No fiscal impact.
BACKGROUND:
East Bay Municipal Utility District shall follow guidelines set forth by the Public Works Department to close Springbrook Road to through traffic for public safety during construction and to expedite the installation of the new water main. The location and alignment of the water mains within these roads and the existing pavement width does not allow for safely keeping the roads open to through traffic during working hours. The infrastructure Renewal Project consists of approximately 4,010' of 6", 8" & 12" water main, service transfer, hydrants and connections.
|