The estimated total project cost is $45 million. Funding in the amount of $12 million is from a federal Health Resources and Services Administration (“HRSA”) grant, provided under the American Recovery and Reinvestment Act of 2009. The remaining balance of $33 million will be provided through bond financing and dedicated revenue within the Hospital Enterprise Fund.
The West County Health Center (“WCHC”) project involves constructing a new 2-story, 53,000-square-foot health center in San Pablo. The new WCHC will serve the region by providing outpatient and ancillary services in a modern and efficient facility. In addition, a new 315-stall, 3-level parking structure will be built adjacent to the WCHC. The “Construction Manager At-Risk” (“CM At-Risk”) project delivery method is being utilized on the project. Utilizing this method involves overlapping multiple design and construction phases in order to fast-track the project. With the CM At-Risk project delivery method, multiple trade bid packages (e.g., earthwork, piles, concrete, framing, mechanical, and electrical) are developed and issued for bidding. Sixteen trade contracts (for earthwork phase 1, pile foundations, general requirements work, structural steel and metal decking, concrete, elevators, miscellaneous metals/stairs, curtain wall, drywall/plaster, fire protection, plumbing, mechanical, electrical, site utilities, roofing/waterproofing/architectural sheet metal, and earthwork phase 2) have already been awarded by the Board. Additional trade bid packages for millwork, doors/frames/hardware, acoustical ceilings, and painting were subsequently developed and issued for bidding.
Bids were received for Trade Bid Packages 5A (millwork), 5D (doors/frames/hardware), 5E (acoustical ceilings), and 5F (painting) and opened by the General Services Department on October 11, 2011. The bid results for Trade Bid Packages 5A, 5D, 5E, and 5F are as follows:
Bidder (Trade Bid Package 5A) |
Base Bid |
Mission Bell Manufacturing, Inc., Morgan Hill |
$563,961 |
Northwestern Design, Grants Pass, OR |
$699,860 |
Bidder (Trade Bid Package 5D) |
Base Bid |
Vila Construction Company, Richmond |
$314,754 |
Bidder (Trade Bid Package 5E) |
Base Bid |
Spacetone Acoustics, Inc., Pleasanton |
$294,295 |
Ad-In Incorporated, Fremont |
$351,500 |
George Family Enterprises, Novato |
$351,848 |
Bidder (Trade Bid Package 5F) |
Base Bid + Additive Alternates to be Awarded (1, 3, 5, 15) |
George E. Masker, Inc., Oakland |
$185,555 |
Blue Skies Painting, San Francisco |
$203,325 |
In addition to the Base Bid scope of work, bidders for Trade Bid Packages 5A (millwork) and 5F (painting) were also required to submit bids on bid alternates that affected them (Additive Alternates #1, 3, 5, 6, and 12 through 15, as highlighted in bold below). The other bid alternates (Additive Alternates #2, 4, and 7 through 11) were previously bid and do not affect Trade Bid Packages 5A, 5D, 5E, and 5F, and therefore pricing for these alternates were not required. The various bid alternates are summarized below:
Bid Alternates |
Summary Description |
Add Alt #1 |
Connecting canopy between clinic and garage. |
Add Alt #2 |
Not applicable to this bid - Trellis on west side of clinic. |
Add Alt #3 |
Patient drop-off canopy. |
Add Alt #4 |
Not applicable to this bid - Trellis on garage upper level. |
Add Alt #5 |
Painting garage stair towers & shear walls |
Add Alt #6 |
Painting garage interior |
Add Alt #7 |
Not applicable to this bid - Lighting at columns & recesses. |
Add Alt #8 |
Not applicable to this bid - Lighting on east & west facades. |
Add Alt #9 |
Not applicable to this bid - Skylights. |
Add Alt #10 |
Not applicable to this bid - Sunshades for south elevation. |
Add Alt #11 |
Not applicable to this bid - Elliptical elevator tower. |
Add Alt #12 |
“Porch Light” elements above check-in areas. |
Add Alt #13 |
Low height divider partitions for waiting areas. |
Add Alt #14 |
Security screens at check-in desks. |
Add Alt #15 |
Accent panels adjacent to exam room doors. |
For Trade Bid Package 5A (millwork), the bids are being evaluated and any award recommendation will be presented to the Board at a future date.
For Trade Bid Package 5D (doors/frames/hardware), one bid was submitted that was $24,754 above the CM At-Risk's estimate of $290,000. Vila submitted the lowest responsive and responsible bid of $314,754. Staff recommends that the trade contract for Trade Bid Package 5D, consisting of doors/frames/hardware, be awarded to Vila for a total contract award amount of $314,754. There were no alternate bid items for Trade Package 5D.
For Trade Bid Package 5E (acoustical ceilings), all Base Bids were above the CM At-Risk's estimate of $290,000. Spacetone submitted the lowest responsive and responsible bid of $294,295, which is $57,205 less than the next lowest bid submitted by Ad-In Incorporated. Staff recommends that the trade contract for Trade Bid Package 5E, consisting of acoustical ceilings, be awarded to Spacetone for a total contract award amount of $294,295. There were no alternate bid items for Trade Bid Package 5E.
For Trade Bid Package 5F (painting), both Base Bids were below the CM At-Risk's estimate of $205,000. Masker submitted the lowest responsive and responsible bid of $169,680 (Base Bid), which is $11,860 less than the next lowest bid submitted by Blue Skies Painting. There were Additive Alternates for Trade Bid Package 5F. The Additive Alternates recommended for award consist of #1, #3, #5, and #15. Although the total amount for the four Additive Alternates would add $15,875, the total cost is still below the Base Bid estimate ($205,000). Staff recommends that the trade contract for Trade Bid Package 5F, consisting of painting, be awarded to Masker and that the award include the Base Bid plus Additive Alternates #1, #3, #5, and #15, for a total contract award amount of $185,555 ($169,680 + $15,875).
With the CM At-Risk project delivery method, the County contracts directly with the various trade contractors, and Turner, as CM At-Risk, manages the trade contracts with a Guaranteed Fixed Price and Guaranteed Completion Date. With award of the above three trade contracts for Trade Bid Packages 5D, 5E, and 5F, the total amount of trade contracts awarded to date is $20,322,983. Recommendations for the award of other trade contracts will come before the Board at future dates.
The County’s CM At-Risk, Turner, has submitted its documentation of good faith efforts to comply with the specifications and requirements of the County's Outreach Program for Trade Bid Packages 5D, 5E, and 5F. Staff recommends the Board determine that Turner, as the CM At-Risk, has documented an adequate good faith effort to comply with the requirements of the Outreach Program and that the Board waive any irregularities relating to the various Outreach steps and Turner’s documentation.
Pursuant to the County’s Project Labor Agreement (PLA) policy, a PLA is required for all trade contracts on this project. Vila, Spacetone, and Masker have signed a PLA, which contains a local hire provision consistent with the Disposition and Development Agreement between the City of San Pablo Redevelopment Agency and the County. As a condition of trade contract award, Vila’s, Spacetone’s, and Masker’s subcontractors will also be required to sign the PLA.
The general prevailing rates of wages, which shall be the minimum rates paid on this project, are on file with the Clerk of the Board, and copies are available to any party upon request.
Failure to award the trade contracts for Trade Bid Packages 5D, 5E, and 5F would delay the project and could potentially result in the WCHC not being built and the loss of $12 million in federal stimulus money.