RECOMMENDATION(S):
APPROVE and AUTHORIZE the Public Works Director, or designee, to execute a contract amendment with Plan B Works, to extend the term from February 2, 2017 through January 9, 2018, and increase the payment limit by $250,000, to a new payment limit of $635,000, to assist in the creation of asset management decision support tools, Countywide.
FISCAL IMPACT:
100% General Fund
BACKGROUND:
On November 17, 2015, the Board of Supervisors approved a contract with Plan B Works for $235,000 to provide business analysis services for the creation of asset management decision support tools. On August 9, 2016, the Board of Supervisors approved an amendment for $150,000, primarily to account for two new deliverables that were not covered in the original contract’s scope of work:
|