C.38
To: Board of Supervisors
From: Julia R. Bueren, Public Works Director/Chief Engineer
Date: May  12, 2009
The Seal of Contra Costa County, CA
Contra
Costa
County
Subject: APPROVE and AUTHORIZE the Public Works Director, or designee, to execute a contract with TRC Engineers, Inc.

APPROVE OTHER
RECOMMENDATION OF CNTY ADMINISTRATOR RECOMMENDATION OF BOARD COMMITTEE

Action of Board On:   05/12/2009
APPROVED AS RECOMMENDED OTHER
Clerks Notes:

VOTE OF SUPERVISORS

AYE:
John Gioia, District I Supervisor
Gayle B. Uilkema, District II Supervisor
Mary N. Piepho, District III Supervisor
Susan A. Bonilla, District IV Supervisor
Federal D. Glover, District V Supervisor
Contact: Kevin Emigh, 313-2233
cc: K. Guruwaya, Construction    
I hereby certify that this is a true and correct copy of an action taken and entered on the minutes of the Board of Supervisors on the date shown.
ATTESTED:     May  12, 2009
David Twa,
 
BY: , Deputy

 

RECOMMENDATION(S):

APPROVE and AUTHORIZE the Public Works Director, or designee, to execute a contract in the amount of $950,000 with TRC Engineers, Inc., to provide construction management services for the Iron Horse Trail Pedestrian Overcrossing Project for the period of May 12, 2009, through October 31, 2010, Pleasant Hill BART area.

FISCAL IMPACT:

There will be no impact on the County General Fund. Funding for the project is as follows:   
  

47.0% Redevelopment funds   





FISCAL IMPACT: (CONT'D)
19.3% Metropolitan Transportation Commission: Housing Incentive Program: Congestion   
Mitigation Air Quality Improvement Program (MTC HIP CMAQ) funds;  
11.6% Regional Bicycle and Pedestrian Program: Congestion Mitigation Air Quality   
Improvements Program (RBPP CMAQ) funds;  
10.6% Measure C funds;   
5.8% Transportation for Livable Communities: Congestion Mitigation   
Air Quality Improvement Program (TLC CMAQ) funds;  
3.8% Transportation Equity Act for the 21st Century: Congestion Mitigation Air Quality   
Improvement Program (TEA 21 CMAQ) funds; and  
1.9% Transportation for Livable Communities: State Transportation Improvement Program –   
Transportation Enhancement (TLC STIP – TE) funds.  

BACKGROUND:

The construction contract for the Iron Horse Trail Pedestrian Overcrossing Project will be awarded on May 12, 2009. Due to the size and magnitude of this project, the County has decided to hire a consulting firm to act as a project manager to represent the County to oversee the construction of the project. The Public Works Department looked into using their own staff, but determined that we currently do not have the resources to complete this task due to the overall complexity of the project.  
  
The Public Works Department went through a consultant selection process. Over 100 consultant firms were solicited to provide a statement of qualifications and proposal to provide construction management services for the Iron Horse Trail Pedestrian Overcrossing Project. From the responses, five firms were shortlisted and interviewed. From this, Public Works felt TRC Engineers, Inc. were most qualified to represent the County.

CONSEQUENCE OF NEGATIVE ACTION:

If the Consulting Services Agreement with TRC Engineers, Inc. is not approved, it may not be possible to complete inspections or construct the project.