The construction contract will be funded by 90.66% Federal FAA AIP Funds, 4% Caltrans, 5.34% Airport Enterprise Funds.
The above project was previously approved by the Board of Supervisors, plans and specifications were filed with the Board, and bids were invited by the Public Works Director. On June 25, 2019, the Public Works Department received bids from the following contractors:
BIDDER, TOTAL AMOUNT, BOND AMOUNTS
Ghilotti Bros., Inc.: $5,534,447.50; Payment: $5,534,447.50; Performance: $5,534,447.50
A Teichert & Sons, Inc. dba Teichert Construction.: $5,589,800.00
DeSilva Gates Construction LP $6,187,687.00
Martin Brothers Construction $6,236,118.25
Granite Rock Company. $6,428,068.00
Bay Cities Paving & Grading, Inc. $6,489,136.30
Ghilotti Construction Co., Inc. $6,554,636.25
Granite Construction Company $6,947,940.70
The bidder listed first above, Ghilotti Bros., submitted the lowest responsive and responsible bid, which is $55,352.50 less than the next lowest bid.
This is a federally funded project subject to a Disadvantaged Business Enterprise (DBE) contract goal and requirements. The Public Works Director reports that the lowest monetary bidder, Ghilotti Bros., attained DBE participation of 6.83% and submitted adequate documentation of good faith efforts to meet the DBE goal (7.00%) and requirements for this project. The Public Works Director recommends that the Board determine that Ghilotti Bros. has demonstrated adequate good faith efforts to meet the DBE goal for this project and has complied with the DBE requirements for this project and recommends that the construction contract be awarded to Ghilotti Bros.
The Public Works Director recommends that the bid submitted by Ghilotti Bros. is the lowest responsive and responsible bid, and this Board concurs and so finds.
The Board of Supervisors previously determined that the project is a California Environmental Quality Act Class 15301(Class I) Categorical Exemption.
The general prevailing rates of wages, which shall be the minimum rates paid on this project, have been filed with the Clerk of the Board, and copies will be made available to any party upon request.
Construction of the project would be delayed, and the project might not be built.