RECOMMENDATION(S):
Acting as the governing board of the Contra Costa County Fire Protection District, APPROVE and AUTHORIZE the Fire Chief, or designee, to execute a contract amendment with RRM Design Group, effective July 23, 2019, to add sub consultant Kimley-Horn Associates, Inc., update the project personnel and billing rates and to increase the payment limit by $300,000 to a new payment limit of $1,240,000 and to extend the term from December 12, 2020, to December 12, 2021, to provide architectural services for new Fire Station No. 9 in Pacheco and Fire Station No. 86 in Bay Point.
FISCAL IMPACT:
$300,000; CCCFPD Capital Construction Fund
BACKGROUND:
In 2016, the Contra Costa County Fire Protection District (District) initiated the process for the design of replacement facilities for Fire Station No. 9 in Pacheco and Fire Station No. 86 in Bay Point.
|